Construction of 2600 sft four bed room two storeyed house at Karukappally Kaloor,Cochin
Saturday, September 20, 2008
Piling details
A hole corresponding to diameter of pile is first dug into the ground.In this case it goes down to 10.5 metres.Then steel reinforcement done is put in place in the 10.5 metre depth hole and then a rich mix of concrete is poured into the hole
No comments: