Friday, July 10, 2009

First Floor Flat roof concreting


Rear portion of first Floor is concreted as flat roof.Balance front portion will be slope roof.Picture shows water being retained on top of concreted surface for curing

Monday, June 1, 2009

First Floor reaching roof level




First Floor brick work has reached roof level.We are providing a less costly outside stair to reach roof by inserting precast stair steps by the side of outer wall one by one till you reach roof top.Picture of this precast outside stair steps being fixed can also be seen

Wednesday, May 13, 2009

First Floor reaching lintel level


Door and window frames for Ground Floor is completely fixed.Door and window frames for First Floor is also being fixed.Balance frames required for First Floor are being manufactured. 28 Pile columns are being raised for first floor .Precast outside stair steps are also being fixed

Tuesday, May 5, 2009

Our Blogs on Kerala Architecture, House construction, interior design, Kerala life, travel and politics

Completed works
http://kerala-houseconstruction-irinjalakuda.blogspot.com/
http://kerala-houseconstruction-cochin.blogspot.com/
Work in progress
http://kerala-houseconstruction-vyttila.blogspot.com/
http://kerala-houseconstruction-nilambur.blogspot.com/
http://kerala-houseconstruction-ranni.blogspot.com/
http://kerala-houseconstruction-josephneroth.blogspot.com/
http://kerala-houseconstruction-sunny.blogspot.com/
http://kerala-houseconstruction-cherthala.blogspot.com/
http://kerala-houseconstruction-elamakkara.blogspot.com/
http://tamilnadu-houseconstruction-ootty.blogspot.com/
Blog and Knoll on Kerala Architecture
http://knol.google.com/k/thomas-viruvelil/kerala-architecture/
http://kerala-architects.blogspot.com/
Blog on Kerala life, Politics, travel and on Kerala Architecture
http://kerala-life.blogspot.com/
DISCLAIMER
Every effort is taken to provide you authentic information on Kerala Architecture and it is features and other relevant information on building a house in Kerala. VIRUVELIL group of Companies or V.H.Thomas or any person interacting through this website on behalf of VIRUVELIL group of companies will not be responsible for the authenticity or correctness of the information provided through this website or conveyed by email to any person contacting us for information, assistance, guidance or for any commercial activity related or followed after any enquiry or request for services /assistance/guidance
We do not accept responsibility for loss or damage arising from the use of the information provided through this website which may be creative work/technical data without our consent/involvement and guidance. We have complete, unchallenged copy right for all information, data, pictures, design details provided through this website. Any dissemination, use, review, distribution, printing or copying in part or full of information, data, pictures design details provided through this website is strictly prohibited.

Monday, April 27, 2009

First Floor brick work reaching lintel level
















First Floor brick work is reaching lintel level.Pictures show work in progress

Friday, March 13, 2009

Slope roof concreting above car porch




Slope roof above car porch is concreted,with provision for Mukhappu.Pictures show concreted area and curing being done after putting jute bags over concreted surface,water soaked

Tuesday, February 24, 2009

Flat roof concreting







Flat roof concreting for Ground Floor done on 23/2.On 24/2,we have constructed brick wall on top of concreted surface for retaining water for curing.Pictures show work for water retension on concrete surface going on and view of building from the front side after ground floor flat roof concreting