Wednesday, September 24, 2008

Temporary shed


Temporary shed is made at site for storage of cement and working tools using coconut leaves,dried and woven as mat

Steel reinforcement for concrete piling


See picture of steel reinforcement done and kept ready for use along with each pile

Piling work continues


Concrete piling has now reached upto 23 piles out of 28

Saturday, September 20, 2008

Piling details



A hole corresponding to diameter of pile is first dug into the ground.In this case it goes down to 10.5 metres.Then steel reinforcement done is put in place in the 10.5 metre depth hole and then a rich mix of concrete is poured into the hole

Concrete piling for Foundation


Permanent single Phase Electric connection obtained and line connected on 21,August,2008

Set out for piling done on 26,August

Well with rings and temporay shed at site

Concrete piling started on 8,September