Tuesday, February 24, 2009

Flat roof concreting







Flat roof concreting for Ground Floor done on 23/2.On 24/2,we have constructed brick wall on top of concreted surface for retaining water for curing.Pictures show work for water retension on concrete surface going on and view of building from the front side after ground floor flat roof concreting

Sunday, February 22, 2009

Ground Floor roof concrete




Work has reached ground floor flat roof concrete level


Picture shows views before roof concreting of Ground Floor

Tuesday, February 17, 2009

Elevation for the house


Picture shows three dimensional elevation for the house under construction

Thursday, February 12, 2009

Sit out beams


Picture shows sit out beams and round columns for sit out

Friday, February 6, 2009

Lintel,flat sunshades and berth slabs







Pictures show lintels,Flat sunshades and berth slabs after concreting.First and second flight of stair is also seen in one of the pictures.After this stage,we have started on brick work above lintel level